Water Plan (Logan Basin) 2026


Queensland Crest

Part 1 Preliminary

1Short title

This plan may be cited as the Water Plan (Logan Basin) 2026.

2Purposes of plan

The purposes of this plan are to—
(a)define the availability of water to which this plan applies; and
(b)provide a framework for sustainably managing water to which this plan applies; and
(c)identify priorities and mechanisms for dealing with the future water requirements in the plan area; and
(d)regulate the taking of, and interference with, surface water, and the taking of underground water, to which this plan applies; and
(e)provide a framework for managing water allocations for surface water to which this plan applies; and
(f)provide access to water resources to support the Traditional Owners of the plan area in achieving their social and cultural aspirations; and
(g)provide a framework for reversing, to the extent practicable, the degradation of natural ecosystems caused by the taking of, or interference with, water to which this plan applies.

3Definitions

The dictionary in schedule 8 defines particular words used in this plan.

4Meaning of surface water

Surface water is water in a watercourse, lake or spring.

Part 2 Plan area, water to which plan applies and other matters

5Water to which plan applies—Act, s 43

(1)For section 43(1)(a) of the Act, this plan applies to the following water—
(a)surface water in the plan area;
(b)underground water in the underground water management area.
(2)However, this plan does not apply to the following water—
(a)water to which the Water Plan (Great Artesian Basin and Other Regional Aquifiers) 2017 applies;
(b)water in springs connected to water mentioned in paragraph (a).

6Plan area

This plan applies to the area shown as the plan area on the map in schedule 1, part 1.

7Subcatchments

(1)The plan area is divided into subcatchments.
(2)Each subcatchment is identified, by a number, on the map in schedule 2, part 1 and is named in schedule 2, part 2.
(3)A subcatchment may be referred to in this plan by its number or by its name.

8Water supply scheme and water supply scheme zones

(1)The part of the plan area shown as the Logan River water supply scheme on the map in schedule 3, part 1 is a water supply scheme for this plan.
(2)A reference in this plan to the Logan River water supply scheme is a reference to the water supply scheme mentioned in subsection (1).
(3)Each part of the Logan River water supply scheme that is shown as a water supply scheme zone on the map in schedule 3, part 2, and named and described in columns 2 and 3 of the table in schedule 3, part 3, is a water supply scheme zone for—
(a)this plan; and
(b)the water supply scheme.
(4)A reference in this plan to a water supply scheme zone by name is a reference to the water supply scheme zone given that name on the map in schedule 3, part 2 and in column 2 of the table in schedule 3, part 3.

9Water management areas—Act, sch 4

(1)For schedule 4 of the Act, definition water management area, paragraph (b), each part of the plan area shown as a water management area on the map in schedule 4, part 1, and named and described in columns 1 and 2 of the table in schedule 4, part 2, is a water management area.
(2)A reference in this plan to a water management area by name is a reference to the water management area given that name on the map in schedule 4, part 1 and in column 1 of the table in schedule 4, part 2.

10Water management area zones

(1)A water management area has 1 or more water management area zones.
(2)Each part of the plan area shown as a water management area zone on the map in schedule 4, part 3, and named and described in columns 2 and 3 of the table in schedule 4, part 4, is a water management area zone for this plan.
(3)A reference in this plan to a water management area zone by name is a reference to the water management area zone given that name on the map in schedule 4, part 3, and in column 2 of the table in schedule 4, part 4.

11Underground water management area

The part of the plan area shown as the Tamborine Mountain (Logan Basin) underground water management area on the map in schedule 5 is the underground water management area for this plan.

12Trading zones—Act, s 43

For section 43(1)(e)(i) of the Act, the following zones are trading zones for water allocations to which this plan applies—
(a)a water supply scheme zone;
(b)a water management area zone.

13Nodes

(1)A node is a location in the plan area set by a model computer program.
(2)The modelled location of each node is identified by a letter on the map in schedule 1, part 2 and is described in the table in schedule 1, part 3.
(3)A node may be referred to in this plan by its letter.

14Information about areas

The location and extent of each of the following is held in digital electronic form on the department’s website—
(a)the plan area;
(b)a subcatchment;
(c)the Logan River water supply scheme;
(d)a water management area;
(e)the underground water management area.

Part 3 Water plan outcomes

15Purpose of part

This part states, for section 43(1)(b) of the Act, the water plan outcomes for this plan.

16General water plan outcome

A water plan outcome for this plan is that water to which this plan applies is to be allocated and managed in a way that—
(a)recognises the natural state of watercourses, lakes, springs and aquifers has changed because of the taking of, or interference with, water; and
(b)seeks to achieve a balance between—
(i)the economic water plan outcomes stated in section 17; and
(ii)the social water plan outcomes stated in section 18; and
(iii)the cultural water plan outcomes stated in section 19; and
(iv)the environmental water plan outcomes stated in section 20; and
(c)improves and promotes understanding of—
(i)the requirements for underground water to support ecosystems dependent on underground water; and
(ii)the flow-related requirements of ecosystems in the plan area; and
(iii)the water required for cultural, spiritual, social and environmental uses of water by the Traditional Owners of the plan area; and
(iv)the water required to deliver social and economic benefits to communities in the plan area; and
(v)the impact of climate change on water availability.

17Water plan outcomes—economic

The economic water plan outcomes for this plan are—
(a)to provide for the continued effect of water entitlements and other authorisations to take or interfere with water; and
(b)to protect the share of water that may be taken under a water allocation; and
(c)to maintain the availability of water for industries dependent on the water resources for the plan area; and
(d)to make water available to support growth in industries dependent on water, including, for example—
(i)agriculture; and
(ii)tourism; and
(e)to maintain and improve trading frameworks to support the effective and efficient operation of the market in water allocations; and
(f)to improve and support the efficient use of water.

18Water plan outcomes—social

The social water plan outcomes for this plan are—
(a)to make water available for future town water supply to towns and communities that rely on the water resources of the plan area; and
(b)to maintain and, to the extent possible, improve—
(i)the availability of water for town water supply to towns and communities that rely on the water resources of the plan area; and
(ii)the flows of water that support water-related aesthetic, community and recreational values; and
(c)to provide water for stock purposes and domestic purposes in the plan area.

19Water plan outcomes—cultural

The cultural water plan outcomes for this plan are—
(a)to maintain flows of water that support the water-related cultural, spiritual, social and environmental values of the Traditional Owners of the plan area; and
(b)to maintain or provide flows of water to support sites of cultural significance in the plan area; and
(c)to maintain or provide flows of water to support species of cultural significance in the plan area.

20Water plan outcomes—environmental

(1)The environmental water plan outcomes for this plan are—
(a)to maintain and, to the extent possible, improve flows of water to which this plan applies that support—
(i)native plants and animals, and their freshwater habitats; and
(ii)riparian systems and their functions; and
(iii)river-forming processes; and
(iv)the health and persistence of waterholes; and
(v)riffle habitats; and
(b)to maintain and, to the extent possible, improve flows of water that support 1 part of a river system to be connected to another—
(i)throughout the watercourse network; and
(ii)within riparian zones, floodplains and associated freshwater habitats, and estuaries; and
(c)to minimise adverse environmental impacts caused by the operation of infrastructure in the plan area; and

Examples of adverse environmental impacts—

degradation of water quality, bank slumping, fish stranding
(d)to maintain and, to the extent possible, improve flows of water to the estuaries in the plan area to—
(i)provide freshwater flow from the plan area to the marine waters of southern Moreton Bay; and
(ii)maintain brackish water estuarine habitat; and
(iii)benefit native estuarine plants and animals; and
(e)for the underground water management area—to maintain the availability and quality of underground water to support ecosystems dependent on the underground water.

Examples of ecosystems for paragraph (e)—

•wetlands
•terrestrial vegetation communities
•continually flowing streams
•ecosystems of which springs form a part
(2)In this section—
waterhole means a part of a watercourse that contains water after the watercourse ceases to flow, other than a part of a watercourse that is within the storage area of a dam on the watercourse.

Part 4 Measures for achieving water plan outcomes

21General measure that contributes to achieving water plan outcomes

A measure that contributes to achieving the water plan outcomes stated in sections 16 to 20 is that, within 5 years after the commencement—
(a)the chief executive considers whether water sharing arrangements should be developed for water entitlements to take surface water that is unsupplemented water in the Albert River and Canungra Creek subcatchments; and
(b)if the chief executive considers the water sharing arrangements should be developed—the water sharing arrangements are developed.

Part 5 Objectives and performance indicators

22Environmental flow objectives and performance indicators—Act, s 43

(1)For section 43(1)(d) of the Act, the environmental flow objectives for surface water to which this plan applies are stated in schedule 6.
(2)The performance indicators for the environmental flow objectives for surface water are stated in schedule 6.

23Water allocation security objectives and performance indicators for surface water—Act, s 43

(1)For section 43(1)(e)(ii) of the Act, the water allocation security objectives for surface water to which this plan applies are that—
(a)for supplemented water—
(i)the performance ratio for each high priority group is not less than 99% of what the performance ratio for the group is on the commencement; and
(ii)the performance ratio for each medium priority group is not less than 95% of what the performance ratio for the group is on the commencement; and
(b)for unsupplemented water—
(i)the performance ratio for the class 1C water allocation group mentioned in section 40(a) is not less than 90% of what the performance ratio for the group is on the commencement; and
(ii)the performance ratio for the class 3C water allocation group mentioned in section 40(b) is not less than 90% of what the performance ratio for the group is on the commencement; and
(iii)the performance ratio for the class 5B water allocation group mentioned in section 40(c) is not less than 90% of what the performance ratio for the group is on the commencement; and
(iv)the performance ratio for the class 6B water allocation group mentioned in section 40(d) is not less than 90% of what the performance ratio for the group is on the commencement.
(2)The performance indicators for the water allocation security objectives mentioned in subsection (1) are the performance ratios for each group of water allocations mentioned in subsection (1)(a)(i) and (ii) and (b)(i) to (iv).
(3)In this section—
average annual volume, of surface water, means the volume of the water expressed as a long-term modelled average over the simulation period for the water.
high priority group means all water allocations to take surface water from the Logan River water supply scheme that state they are in the ‘high priority group’.
medium priority group means all water allocations to take surface water from the Logan River water supply scheme that state they are in the ‘medium priority group’.
performance ratio, for a group of water allocations, means the average annual volume of water that may be taken by holders of all water allocations in the group in the simulation period expressed as a percentage of the total of the nominal volume for all water allocations in the group.

Part 6 Strategies for achieving water plan outcomes for surface water

24Definition for part

In this part—
decision means a decision made by the chief executive under chapter 2 of the Act about—
(a)a water allocation, or resource operations licence, for surface water to which this plan applies; or
(b)an operations manual required under a resource operations licence mentioned in paragraph (a).

25Decisions must be consistent with particular objectives

A decision must be consistent with—
(a)the environmental flow objectives stated in section 22(1); and
(b)the water allocation security objectives stated in section 23(1).

26Assessing consistency with particular objectives

(1)To assess the consistency of a decision with the environmental flow objectives and the water allocation security objectives, the model computer program’s simulation for the simulation period must be used.
(2)If it is not practicable to use the model computer program’s simulation, another kind of assessment approved by the chief executive may be used.

Part 7 Limitations on taking or interfering with water

27Limitations on taking or interfering with underground water in underground water management area—Act, s 101

(1)For section 101(1) of the Act, a person must not, under section 101(1)(c) of the Act, take or interfere with underground water in the underground water management area unless the water is taken or interfered with for—
(a)stock purposes or domestic purposes; or
(b)agricultural purposes if the area to be irrigated is less than 10 hectares; or
(c)town water supply purposes in the plan area; or
(d)a coordinated project; or
(e)if the underground water is taken or interfered with using existing underground water works—a lawful purpose for which underground water was, immediately before the commencement, being taken or interfered with using the works.
(2)In this section—
coordinated project see the State Development and Public Works Organisation Act 1971, schedule 2.
existing underground water works—
(a)means works that—
(i)are used, or are capable of being used, to take or interfere with underground water to which this plan applies; and
(ii)were in existence before the commencement; and
(iii)are not altered after the commencement; and
(iv)have not been constructed or altered in contravention of the Tamborine Mountain and Springbrook areas moratorium notice; and
(b)includes a replacement water bore that replaces works mentioned in paragraph (a).
replacement water bore see the Water Regulation 2016, schedule 19.
Tamborine Mountain and Springbrook areas moratorium notice means the moratorium notice dated 6 March 2020, called ‘Moratorium notice Water Act 2000 section 30 Tamborine Mountain and Springbrook areas’.

Part 8 Unallocated water

28Unallocated water reserved under this plan—Act, s 43

For section 43(1)(c) of the Act, the total volume of unallocated water reserved under this plan is 0ML.

Part 9 Water licences

Division 1 Applications for water licences that must not be accepted

29Chief executive must not accept particular applications—Act, s 43

For section 43(2)(j) of the Act, the chief executive must not accept an application for a water licence made under section 107 of the Act unless—
(a)the application is for a water licence that will state the purpose of ‘relift’; or
(b)the application is for a water licence to interfere with the flow of surface water by diversion; or
(c)the application is for a water licence to interfere with the flow of surface water, other than by diversion, that is mentioned in section 30.

30Particular applications to interfere with flow of surface water other than by diversion

(1)This section applies in relation to an application, made under section 107 of the Act, for a water licence to interfere with the flow of surface water to which this plan applies other than by diversion.
(2)The chief executive may accept the application if—
(a)the applicant is a local government or the bulk water supply authority; and
(b)the purpose of the proposed interference is to enable the applicant to lawfully construct or maintain infrastructure to improve security for town water supplies in the plan area.
(3)The chief executive may also accept the application if the proposed interference—
(a)has been continuous from immediately before the commencement; and
(b)is not authorised under a water licence to interfere with the flow of surface water to which this plan applies.

Division 2 Applications inconsistent with this plan

31Particular applications for dealings inconsistent with this plan

(1)The granting of an application made under section 121 of the Act for a dealing with a water licence in relation to surface water to which this plan applies is inconsistent with this plan if the application is an application for a dealing mentioned in section 130(1)(a) of the Act.

Note—

See section 129 of the Act for the actions the chief executive must take if the granting of an application for a dealing with a water licence is inconsistent with a water plan.
(2)However, subsection (1) does not apply to any of the following applications—
(a)an application the chief executive may decide to grant under section 33;
(b)an application for a dealing with a water licence permitted under the water management protocol for this plan.
(3)Also, subsection (1) does not apply to an application made by a local government or the bulk water supply authority to do either of the following for the purpose of enabling the applicant to lawfully supply town water to towns and communities dependent on the water resources for the plan area—
(a)increase the rate of the taking of surface water to which this plan applies;
(b)change the location of the taking or interference with water under the licence.

Note—

See section 130 of the Act for how an application mentioned in subsection (2) or (3) must be assessed.

Division 3 Granting particular water licences

32Water licences stated in water entitlement notice—Act, s 116

For section 116(1) of the Act, the chief executive must decide to grant a water licence to take, or interfere with the flow of, water to which this plan applies if a water entitlement notice for this plan provides for the granting of the licence.

Note—

See also section 116(2) of the Act for when the chief executive may grant a water licence without the need for an application to be made under section 107 of the Act.

Division 4 Applications for seasonal water assignments

33Deciding applications for seasonal water assignments—Act, s 43

For section 43(2)(i) of the Act, the chief executive may decide to grant an application for a seasonal water assignment of a water licence if the seasonal water assignment of the licence is permitted under the water management protocol for this plan.

Division 5 Content and conditions of water licences to take surface water

34Application of division

This division applies to a water licence that—
(a)was in effect immediately before the commencement; and
(b)on the commencement, authorises the taking of surface water to which this plan applies.

35Content and conditions of water licence

(1)The water licence must state—
(a)the purpose for which water may be taken under the licence, as required under section 36; and
(b)the nominal entitlement for the licence worked out under section 37; and
(c)the maximum rate at which the water may be taken under the licence worked out under section 38; and
(d)the conditions, if any, for the licence.
(2)However—
(a)subsection (1)(b) and (c) does not apply if the purpose required for the licence under section 36 is ‘relift’; and
(b)subsection (1)(c) does not apply if—
(i)the purpose required for the licence under section 36 is ‘town water supply’; and
(ii)immediately before the commencement, the licence did not state, whether as a condition or otherwise, a maximum rate for taking water.

36Purpose to be stated on water licence

The purpose for which water may be taken under the water licence, that is to be stated on the licence, must be—
(a)if, immediately before the commencement, the only purpose stated on the licence was ‘stock’, ‘domestic supply’ or ‘stock and domestic supply’—either or both of the following purposes—
(i)‘stock’;
(ii)‘domestic’; or
(b)if, immediately before the commencement, the only purpose stated on the licence was ‘town water supply’ or ‘urban’—‘town water supply’; or
(c)if, immediately before the commencement, the only purpose stated on the licence was ‘relift’—‘relift’; or
(d)otherwise—‘any’.

37Nominal entitlement for water licence

(1)Subject to subsections (2) and (4), the nominal entitlement for the water licence must be—
(a)if, immediately before the commencement, the licence stated, whether as a condition or otherwise, the total volume of water that may be taken under the licence in a water year—the stated volume; or
(b)if paragraph (a) does not apply and, immediately before the commencement, the only purpose for which water may be taken under the licence was ‘stock’, ‘domestic supply’ or ‘stock and domestic supply’—1ML; or
(c)if paragraphs (a) and (b) do not apply and, immediately before the commencement, the licence stated an area, in hectares, that may be irrigated by water taken under the licence—the volume of water calculated by multiplying the stated area by 6; or
(d)if paragraphs (a), (b) and (c) do not apply and the maximum rate at which surface water may be taken under the licence is worked out under section 38(2) to (5)—the volume of water calculated by multiplying the maximum rate by 30.
(2)The nominal entitlement for water licence number 47454C must be 60ML.
(3)Subsection (4) applies in relation to the water licence if—
(a)the nominal entitlement for the licence can not be worked out under subsections (1) or (2); or
(b)both of the following apply—
(i)subsection (1)(a) does not apply in relation to the licence;
(ii)the chief executive is satisfied that the nominal entitlement for the licence, worked out under subsection (1)(b), (c) or (d), is not sufficient for the purpose for which water may be taken under the licence.
(4)The nominal entitlement for the water licence must be the volume of water decided by the chief executive, after considering the matters stated in subsection (5).
(5)For subsection (4), the matters are—
(a)the purpose required for the licence under section 36; and
(b)the volume of water required for the purpose mentioned in paragraph (a); and
(c)the efficiency of the water use associated with water that may be taken under the water licence; and
(d)the conditions under which water may be taken under the water licence, including, for example, flow conditions; and
(e)the water-taking capacity, under normal operating conditions, of relevant works that relate to an activity authorised under the water licence; and
(f)the local availability of water.
(6)The nominal entitlement for the water licence must be expressed in the licence in megalitres.
(7)In this section—
relevant works means works—
(a)used, or capable of being used, to take water to which this plan applies; and
(b)that were in existence immediately before the commencement.

38Maximum rate for taking surface water

(1)Subject to subsections (2) and (3), the maximum rate at which surface water may be taken under the water licence must be—
(a)if the purpose required for the licence under section 36 is ‘town water supply’ and the licence states, whether as a condition or otherwise, a maximum rate for taking water—the stated rate; or
(b)if the purpose required for the licence under section 36 is ‘stock’, ‘domestic’ or ‘any’ and the nominal entitlement for the licence is worked out under section 37(1)(a), (b) or (c) or (2)—the volume of water calculated by dividing the nominal entitlement for the licence by 30.
(2)If the maximum rate at which surface water may be taken under the water licence can not be worked out under subsection (1), the maximum rate at which surface water may be taken under the licence must be the rate decided by the chief executive after considering the matters stated in subsection (3).
(3)For subsection (2), the matters are—
(a)if the water licence states, whether as a condition or otherwise, a maximum rate for taking water—the stated rate; or
(b)if paragraph (a) does not apply and a development permit for works for taking water under the water licence states, whether as a condition or otherwise, a pump size mentioned in the Water Regulation 2016, schedule 7, column 1 (each a standard pump size)—the rate stated in the Water Regulation 2016, schedule 7, column 3 for the standard pump size; or
(c)if paragraphs (a) and (b) do not apply and a development permit for works for taking water under the water licence states, whether as a condition or otherwise, a pump size other than the standard pump size—the rates stated in the Water Regulation 2016, schedule 7, column 3 for similar pump sizes; or
(d)if paragraphs (a), (b) and (c) do not apply and the water licence states other conditions applying to the taking of water under the licence, including, for example, flow conditions—the other conditions; or
(e)if paragraphs (a), (b), (c) and (d) do not apply and a development permit for works for taking water under the water licence states, whether as a condition or otherwise, a pump size—the water-taking capacity of a pump of the stated size under normal operating conditions; or
(f)if paragraphs (a), (b), (c), (d) and (e) do not apply and other infrastructure is associated with the taking of water under the water licence—the other infrastructure; or
(g)if paragraphs (a), (b), (c), (d), (e) and (f) do not apply—any other matter the chief executive considers relevant.
(4)For subsection (3)(b), (c) or (e), if there are 2 or more development permits for works for taking water under the water licence, or if a development permit states 2 or more pump sizes, the chief executive must only apply subsection (3)(b), (c) or (e) to the largest pump size stated in any of the permits.
(5)The maximum rate at which water to which this plan applies may be taken under the water licence must be expressed in the licence in megalitres per day, rounded up to the nearest first decimal point.

39Conditions for water licences amended or replaced by the chief executive

(1)This section applies if the chief executive decides to amend or replace the water licence under section 133 of the Act for consistency with this plan.
(2)When making a decision about the conditions that will apply to the amended or new water licence, the chief executive must have regard to the content and conditions of the water licence mentioned in subsection (1), as in force immediately before the commencement.

Part 10 Water allocations

40Water allocation groups—Act, sch 4

For schedule 4 of the Act, definition water allocation group—
(a)a water allocation to take surface water that is unsupplemented water in the Burnett Creek water management area belongs to the class 1C water allocation group; and
(b)a water allocation to take surface water that is unsupplemented water in the Logan River water management area belongs to the class 3C water allocation group; and
(c)a water allocation to take surface water that is unsupplemented water in the Running Creek water management area belongs to the class 5B water allocation group; and
(d)a water allocation to take surface water that is unsupplemented water in the Christmas Creek water management area belongs to the class 6B water allocation group.

41Amending particular water allocations—Act, s 150

(1)This section applies to a water allocation mentioned in schedule 7.
(2)For section 150(1)(a) of the Act, the water allocation must be amended to ensure—
(a)if column 2 of the table in schedule 7 states a maximum rate of take for the water allocation—the maximum rate is the stated rate; and
(b)if column 2 of the table in schedule 7 states a water allocation group for the water allocation—the water allocation group is the stated water allocation group.
(3)To remove any doubt, it is declared that if an existing element of the water allocation is inconsistent with an amendment required under subsection (2), the existing element must be also amended or removed, but only to the extent necessary to avoid the inconsistency.

42Amending other water allocations to state particular information—Act, s 150

(1)This section applies to a water allocation to take surface water that is unsupplemented water to which this plan applies, other than a water allocation mentioned in schedule 7, if the water allocation does not state—
(a)the maximum rate of take, expressed in megalitres per day, for the water allocation; or
(b)the water allocation group for the water allocation.
(2)For section 150(1)(a) of the Act, the water allocation must be amended to ensure the water allocation states—
(a)if subsection (1)(a) applies—the maximum rate, expressed in megalitres per day rounded up to 1 decimal place, for the water allocation; or
(b)if subsection (1)(b) applies—the water allocation group for the water allocation.
(3)For subsection (2)(a), if the water allocation states a maximum rate, expressed in litres per second (the stated rate), the maximum rate must be calculated by multiplying the stated rate by 0.0864.

Part 11 Miscellaneous

43Water management protocol—Act, s 43

(1)For section 43(2)(1) of the Act, a water management protocol must be prepared for the plan area.
(2)The water management protocol must state the following matters for the plan area—
(a)the criteria and process for deciding applications for a seasonal water assignment;
(b)the water allocation dealing rules.

44Amendments to plan that may be made without consultation—Act, s 43

For section 43(2)(m) of the Act, the following amendments may be made to this plan without public consultation—
(a)an amendment or addition of an environmental flow objective or a water allocation security objective, or a performance indicator for an objective, if the amendment or addition achieves an equivalent or improved environmental flow and water allocation security outcome;
(b)an amendment or addition of a node;
(c)an amendment or addition of a priority group mentioned in section 23;
(d)an amendment to adjust the boundaries of the following areas if more accurate information about the geographic or hydrological characteristics of the areas becomes available—
(i)the plan area;
(ii)the Logan River water supply scheme;
(iii)a water supply scheme zone;
(iv)a water management area;
(v)a water management area zone;
(vi)the underground water management area;
(vii)a subcatchment;
(e)an amendment to change the period within which a measure for achieving a stated water plan outcome is to be achieved;
(f)an amendment to remove a provision of this plan that no longer has effect.

45Definition of position

(1)In this plan, position is defined by reference to GDA2020.
(2)In this section—
GDA2020 means the Reference Frame under the National Measurement (Recognized-Value Standard of Measurement of Position) Determination 2026 (Cwlth) as in force on 9 March 2026.

Part 12 Repeal and transitional provisions

Division 1 Repeal

46Repeal

The Water Plan (Logan Basin) 2007, SL No. 25 is repealed.

Division 2 Transitional provisions

47Definition for division

In this division—
repealed plan means the repealed Water Plan (Logan Basin) 2007.

48Applications for water licences made before commencement

(1)This section applies to an application for a water licence to take or interfere with water to which the repealed plan applied if the application was made, but not decided, before the commencement.
(2)If the chief executive would not, under section 29, be able to accept the application had it been made after the commencement, the application is of no effect and is taken not to have been made.
(3)If subsection (2) does not apply, the application must be decided under this plan.

49Applications for dealings with water licences made before commencement

(1)This section applies to an application for a dealing with a water licence to take or interfere with water to which the repealed plan applied if the application was made, but not decided, before the commencement.
(2)If the granting of the application would be inconsistent with this plan had the application been made after the commencement, the application is inconsistent with this plan.

Note—

See section 129 of the Act for the actions the chief executive must take if granting an application for a dealing with a water licence would be inconsistent with a water plan.
(3)If subsection (2) does not apply, the application must be decided under this plan.

Schedule 1 Plan area and nodes

sections 6 and 13(2)

Part 1 Plan area

graphic image

Part 2 Nodes

graphic image

Part 3 Locations of nodes

Column 1

Column 2

Node

Modelled locations

A

Logan River at Rathdowney gauging station 145020A (28.2155° south, 152.8679° east)

B

Logan River at Yarrahappini gauging station 145014A (27.8336° south, 152.9877° east)

C

Logan River at Round Mountain gauging station 145008A (28.0708° south, 152.9273° east)

D

Logan River at end of system (27.6964° south, 153.3391° east)

E

Cainbable Creek at The Gorge gauging station 145103A (28.0949° south, 153.0773° east)

F

Albert River at Lumeah No. 2 gauging station 145101D (28.0542° south, 153.0446° east)

G

Albert River at Bromfleet gauging station 145102B (27.9092° south, 153.1065° east)

H

Albert River at end of system (27.6959° south, 153.2405° east)

I

Teviot Brook at Croftby gauging station 145011A (28.1480° south, 152.5701° east)

J

Canungra Creek at Main Road Bridge gauging station 145107A (27.9976° south, 153.1583° east)

K

Christmas Creek at Tramway Lane gauging station 145026A (28.1489° south, 152.9717° east)

L

Burnett Creek at Upstream Maroon Dam gauging station 145018A (28.2196° south, 152.6085° east)

M

Logan River at Forest Home gauging station 145003B (28.2001° south, 152.7725° east)

N

Palen Creek at Ward Road gauging station 145027A (28.2475° south, 152.8396° east)

O

Running Creek at Dieckmans Bridge gauging station 145010A (28.2453° south, 152.8907° east)

Schedule 2 Subcatchments

section 7(2)

Part 1 Area of subcatchments

graphic image

Part 2 Names of subcatchments

Column 1

Column 2

Subcatchment area

Subcatchment name

1

Burnett Creek

2

Upper Logan River

3

Logan River

4

Palen Creek

5

Running Creek

6

Christmas Creek

7

Teviot Brook

8

Albert River

9

Canungra Creek

10

Redlands subcatchments

Schedule 3 Water supply scheme and water supply scheme zones

section 8

Part 1 Logan River water supply scheme

graphic image

Part 2 Water supply scheme zones

graphic image

Part 3 Description of water supply scheme zones

Column 1

Column 2

Column 3

Water supply scheme

Name of water supply scheme zone

Description of water supply scheme zone

Logan River

Logan Zone A

Logan River between—

(a)  its confluence with Running Creek (28.2107° south, 152.8789° east); and
(b)  its confluence with Burnett Creek (28.1956° south, 152.7770° east).

Logan River

Logan Zone B

Logan River between—

(a)  its confluence with Christmas Creek (28.1162° south, 152.9342° east); and
(b)  its confluence with Running Creek (28.2107° south, 152.8789° east).

Logan River

Logan Zone C

Logan River between—

(a)  Bromelton Weir (28.0064° south, 152.9465° east); and
(b)  its confluence with Christmas Creek (28.1162° south, 152.9342° east).

Logan River

Logan Zone D

Logan River between—

(a)  the imaginary line that crosses the river at 27.9397° south, 152.9465° east; and
(b)  Bromelton Weir (28.0064° south, 152.9465° east).

Logan River

Logan Zone E

Logan River between—

(a)  its confluence with Teviot Brook (27.8434° south, 152.9464° east); and
(b)  the imaginary line that crosses the river at 27.9397° south, 152.9733° east.

Logan River

Logan Zone F

Logan River between—

(a)  the imaginary line that crosses the river at 27.8399° south, 152.9652° east; and
(b)  its confluence with Teviot Brook (27.8434° south, 152.9464° east).

Logan River

Logan Zone G

Logan River between—

(a)  the Mount Lindesay Highway crossing (27.7851° south, 153.0122° east); and
(b)  the imaginary line that crosses the river at 27.8399° south, 152.9652° east.

Logan River

Burnett Zone A

Burnett Creek between—

(a)  the dam wall of Maroon Dam (28.1811° south, 152.6564° east); and
(b)  the ponded limit of the storage area of Maroon Dam (28.2041° south, 152.6228° east).

Logan River

Burnett Zone B

Burnett Creek between—

(a)  its confluence with Logan River (28.1956° south, 152.7770° east); and
(b)  the dam wall of Maroon Dam (28.1811° south, 152.6564° east).

Logan River

Teviot Zone A

Teviot Brook between—

(a)  the dam wall of Wyaralong Dam (27.9087° south, 152.8826° east); and
(b)  the ponded limit of the storage area of Wyaralong Dam (27.9520° south, 152.7404° east).

Logan River

Teviot Zone B

Teviot Brook between—

(a)  its confluence with Logan River (27.8434° south, 152.9464° east); and
(b)  the dam wall of Wyaralong Dam (27.9087° south, 152.8826° east).

Schedule 4 Water management areas and water management area zones

sections 9 and 10

Part 1 Water management areas

graphic image

Part 2 Description of water management area

Column 1

Column 2

Water management area

Description of water management area

Burnett Creek

Burnett Creek between—

(a)  the imaginary line that crosses the creek at 28.1953° south, 152.7748° east; and
(b)  the dam wall of Maroon Dam (28.1811° south, 152.6564° east).

Christmas Creek

Christmas Creek between—

(a)  its confluence with Logan River (28.1162° south, 152.9342° east); and
(b)  the confluence of Christmas Creek (North Branch) and Christmas Creek (South Branch) (28.2928° south, 153.0963° east).
Chinghee Creek between—
(a)  its confluence with Christmas Creek (28.2379° south, 152.9925° east); and
(b)  the imaginary line that crosses the creek at 28.2761° south, 152.9754° east.
Widgee Creek between—
(a)  its confluence with Christmas Creek (28.2140° south, 152.9754° east); and
(b)  the imaginary line that crosses the creek at 28.2722° south, 153.0790° east.

Logan River

Logan River between—

(a)  the Mount Lindesay Highway crossing (27.7851° south, 153.0122° east); and
(b)  its confluence with Burnett Creek (28.1956° south, 152.7770° east).
Burnett Creek between—
(a)  its confluence with Logan River (28.1956° south, 152.7770° east); and
(b)  the imaginary line that crosses the creek at 28.1953° south, 152.7748° east.

Running Creek

Running Creek between—

(a)  its confluence with Logan River (28.2107° south, 152.8789° east); and
(b)  the confluence of Running Creek (North Branch) and Running Creek (South Branch) (28.3225° south, 153.0455° east).

Part 3 Water management area zones

graphic image

Part 4 Description of water management area zones

Column 1

Column 2

Column 3

Water management area

Water management area zone

Description of water management area zone

Burnett Creek

Burnett Zone CA

Burnett Creek between—

(a)  the imaginary line that crosses the creek at 28.1953° south, 152.7748° east; and
(b)  the dam wall of Maroon Dam (28.1811° south, 152.6564° east).

Christmas Creek

Christmas Zone CA

Christmas Creek between—

(a)  its confluence with Logan River (28.1162° south, 152.9342° east); and
(b)  the confluence of Christmas Creek (North Branch) and Christmas Creek (South Branch) (28.2928° south, 153.0963° east).
Chinghee Creek between—
(a)  its confluence with Christmas Creek (28.2379° south, 152.9925° east); and
(b)  the imaginary line that crosses the creek at 28.2761° south, 152.9754° east.
Widgee Creek between—
(a)  its confluence with Christmas Creek (28.2140° south, 152.9754° east); and
(b)  the imaginary line that crosses the creek at 28.2722° south, 153.0790° east.

Logan River

Logan Zone CA

Logan River between—

(a)  its confluence with Burnett Creek (28.1956° south, 152.7770° east); and
(b)  the Running Creek Road crossing (28.2135° south, 152.8732° east).
Burnett Creek between—
(a)  its confluence with Logan River (28.1956° south, 152.7770° east); and
(b)  the imaginary line that crosses the river at 28.1953° south, 152.7748° east.

Logan River

Logan Zone CB

Logan River between—

(a)  the imaginary line that crosses the river at 28.1209° south, 152.9340° east; and
(b)  the Running Creek Road crossing (28.2135° south, 152.8732° east).

Logan River

Logan Zone CC

Logan River between—

(a)  Bromelton Weir (28.0064° south, 152.9465° east); and
(b)  the imaginary line that crosses the river at 28.1209° south, 152.9340° east.

Logan River

Logan Zone CD

Logan River between—

(a)  the Allan Creek Road crossing (27.9386° south, 152.9733° east); and
(b)  Bromelton Weir (28.0064° south, 152.9465° east).

Logan River

Logan Zone CE

Logan River between—

(a)  Cedar Grove Weir (27.8475° south, 152.9769° east); and
(b)  the Allan Creek Road crossing (27.9386° south, 152.9733° east).

Logan River

Logan Zone CF

Logan River between—

(a)  South Maclean Weir (27.8067° south, 153.0236° east); and
(b)  Cedar Grove Weir (27.8475° south, 152.9769° east).

Logan River

Logan Zone CG

Logan River between—

(a)  the Mount Lindesay Highway crossing (27.7851° south, 153.0122° east); and
(b)  South Maclean Weir (27.8067° south, 153.0236° east).

Running Creek

Running Zone CA

Running Creek between—

(a)  its confluence with Logan River (28.2107° south, 152.8789° east); and
(b)  the confluence of Running Creek (North Branch) and Running Creek (South Branch) (28.3225° south, 153.0455° east).

Schedule 5 Underground water management area

section 11

graphic image

Schedule 6 Environmental flow objectives and performance indicators

section 22

1Mean annual flow

(1)An environmental flow objective for surface water to which this plan applies is that, at each node stated in column 1 of table 1, the performance indicator mentioned in subsection (2) must be at least the percentage, of the pre-development flow, that is stated in column 2 of the table opposite the node.
(2)The performance indicator is the mean annual flow.
(3)In this section—
mean annual flow, at a node, means the total volume of flow of water at the node in the simulation period divided by the number of years in the simulation period.
pre-development flow, for a node, means the mean annual flow at the node, during the simulation period, simulated as if—
(a)there were no dams or other water infrastructure in the plan area; and
(b)no water had been taken under authorisations in the plan area.

Table 1

Column 1

Column 2

Node

Percentage

A

91

B

73

C

84

D

81

E

92

F

88

G

82

H

84

I

96

J

95

K

79

L

99

M

99

N

89

O

89

2Days in low flow periods

(1)An environmental flow objective for surface water to which this plan applies is that, at each node stated in column 1 of table 2, the performance indicator mentioned in subsection (2) must be no more than the percentage, of the total number of days in the simulation period, that is stated in column 4 of the table opposite the node.
(2)The performance indicator is the total number of days in low flow periods.
(3)In this section—
daily low flow volume, for a node, means the volume that is stated in column 2 of table 2 opposite the node.
low flow period, for a node, means a continuous period—
(a)that is more than the number of days stated in column 3 of table 2 opposite the node; and
(b)that is during the simulation period; and
(c)during which daily water flows at the node are no more than the daily low flow volume for the node.

Table 2

Column 1

Column 2

Column 3

Column 4

Node

Volume (ML)

Duration (days)

Percentage

B

4

30

35.6

C

4

30

4.0

E

2

90

48.9

F

4

60

36.5

G

4

60

18.9

I

2

90

28.4

J

4

30

10.6

K

2

30

2.4

L

2

30

5.8

M

4

60

10.4

N

2

90

44.8

O

2

30

0.3

3Days in migration flow periods

(1)An environmental flow objective for surface water to which this plan applies is that at each node stated in column 1 of table 3—
(a)the performance indicator mentioned in subsection (2)(a) must be no more than the percentage, of the total number of days in the Oct–May water flow season, that is stated in column 3 of the table opposite the node; and
(b)the performance indicator mentioned in subsection (2)(b) must be no more than the percentage, of the total number of days in the Jun–Sep water flow season, that is stated in column 5 of the table opposite the node.
(2)The performance indicator is the total number of days in migration flow periods during—
(a)the Oct–May water flow season; or
(b)the Jun–Sep water flow season.
(3)In this section—
Jun–Sep water flow season means the period—
(a)starting on 1 June; and
(b)ending on 30 September.
migration flow period, for a node, means a continuous period—
(a)that is more than—
(i)for the Oct–May water flow season—30 days; and
(ii)for the Jun–Sep water flow season—60 days; and
(b)that is during the simulation period; and
(c)during which daily water flows at the node are no more than the daily flow volume stated in—
(i)for the Oct–May water flow season—column 2 of table 3 opposite the node; and
(ii)for the Jun–Sep water flow season—column 4 of table 3 opposite the node.
Oct–May water flow season means the period—
(a)starting on 1 October; and
(b)ending on 31 May.

Table 3

Column 1

Column 2

Column 3

Column 4

Column 5

Node

Daily flow volume for Oct–May water flow season (ML)

Percentage for Oct–May water flow season

Daily flow volume for Jun–Sep water flow season (ML)

Percentage for Jun–Sep water flow season

B

224

60.3

8,640

96.9

G

224

74.5

8,640

99.0

4Days in estuarine salinity periods

(1)An environmental flow objective for surface water to which this plan applies is that at each node stated in column 1 of table 4 the performance indicator mentioned in subsection (2) must be no more than the percentage, of the total number of days in the Oct–May water flow season, that is stated in column 3 of the table opposite the node.
(2)The performance indicator is the total number of days in estuarine salinity periods during the Oct–May water flow season.
(3)In this section—
estuarine salinity period, for a node, means a continuous period for the Oct–May water flow season—
(a)that is more than 120 days; and
(b)that is during the simulation period; and
(c)during which daily water flows at the node are no more than the daily flow volume stated in column 2 of table 4 opposite the node.
Oct–May water flow season means the period—
(a)starting on 1 October; and
(b)ending on 31 May.

Table 4

Column 1

Column 2

Column 3

Node

Daily flow volume for Oct–May water flow season (ML)

Percentage for Oct–May water flow season

B

1,250

58.3

G

450

63.7

5Days in riparian vegetation flow periods

(1)An environmental flow objective for surface water to which this plan applies is that, at each node stated in column 1 of table 5, the performance indicator mentioned in subsection (2) must be no more than the percentage, of the total number of days in the simulation period, that is stated in column 3 of the table opposite the node.
(2)The performance indicator is the total number of days in riparian vegetation flow periods.
(3)In this section—
riparian vegetation flow period, for a node, is a continuous period—
(a)of more than 1 year; and
(b)that is during the simulation period; and
(c)during which daily water flows at the node are no more than the daily flow volume stated in column 2 of table 5 opposite the node.

Table 5

Column 1

Column 2

Column 3

Node

Daily flow volume (ML)

Percentage

A

5,329

77.8

B

23,501

81.0

C

1,519

26.2

E

428

57.6

F

3,444

74.3

G

9,750

76.3

I

1,063

73.4

J

2,200

70.8

K

569

38.9

L

852

77.3

M

3,482

73.8

N

679

81.3

O

1,020

46.0

6Days in floodplain vegetation flow periods

(1)An environmental flow objective for surface water to which this plan applies is that, at each node stated in column 1 of table 6, the performance indicator mentioned in subsection (2) must be no more than the percentage, of the total number of days in the simulation period, that is stated in column 3 of the table opposite the node.
(2)The performance indicator is the total number of days in floodplain vegetation flow periods.
(3)In this section—
floodplain vegetation flow period, for a node, is a continuous period—
(a)of more than 1 year; and
(b)that is during the simulation period; and
(c)during which daily water flows at the node are no more than the daily flow volume stated in column 2 of table 6 opposite the node.

Table 6

Column 1

Column 2

Column 3

Node

Daily flow volume (ML)

Percentage

A

23,306

99.8

B

81,716

98.4

C

42,645

98.5

E

4,200

95.9

F

12,724

96.2

G

36,551

96.2

I

4,363

98.9

J

6,750

96.2

K

7,322

97.0

L

4,650

97.8

M

11,100

96.2

N

4,100

96.4

O

8,676

96.8

7Days in river-forming flow periods

(1)An environmental flow objective for surface water to which this plan applies is that, at each node stated in column 1 of table 7, the performance indicator mentioned in subsection (2) must be at least the percentage, of the total number of days in the simulation period, that is stated in column 3 of the table opposite the node.
(2)The performance indicator is the total number of days in river-forming flow periods.
(3)In this section—
river-forming flow period, for a node, is a continuous period—
(a)that is during the simulation period; and
(b)during which daily water flows at the node are more than the daily flow volume stated in column 2 of table 7 opposite the node.

Table 7

Column 1

Column 2

Column 3

Node

Daily flow volume (ML)

Percentage

A

15,034

0.105

B

47,174

0.215

C

28,598

0.164

E

2,454

0.190

F

8,986

0.142

G

20,503

0.229

I

3,067

0.166

J

4,139

0.228

K

5,184

0.166

L

1,763

0.350

M

5,858

0.277

N

1,642

0.234

O

6,912

0.150

Schedule 7 Water allocations that must be amended

section 41

Column 1

Column 2

Water allocation

Detail or condition

171 on AP14819

Maximum rate of take: 2.2ML per day

172 on AP14819

Maximum rate of take: 13.9ML per day

173 on AP14819

Maximum rate of take: 4.4ML per day

174 on AP14819

Maximum rate of take: 7.4ML per day

175 on AP14819

Maximum rate of take: 4.4ML per day

176 on AP14819

Maximum rate of take: 4.4ML per day

177 on AP14819

Maximum rate of take: 1.2ML per day

178 on AP14819

Maximum rate of take: 4.4ML per day

179 on AP14819

Maximum rate of take: 4.4ML per day

180 on AP14819

Maximum rate of take: 7.4ML per day

181 on AP14819

Maximum rate of take: 4ML per day

182 on AP14819

Maximum rate of take: 7.4ML per day

183 on AP14819

Maximum rate of take: 12.1ML per day

184 on AP14819

Maximum rate of take: 4.4ML per day

185 on AP14819

Maximum rate of take: 4.4ML per day

186 on AP14819

Maximum rate of take: 4.4ML per day

187 on AP14819

Maximum rate of take: 13ML per day

188 on AP14819

Maximum rate of take: 4.4ML per day

189 on AP14819

Maximum rate of take: 4.4ML per day

191 on AP14819

Maximum rate of take: 4.4ML per day

192 on AP14819

Maximum rate of take: 4ML per day

193 on AP14819

Maximum rate of take: 4.4ML per day

194 on AP14819

Maximum rate of take: 4.4ML per day

195 on AP14819

Maximum rate of take: 7.4ML per day

196 on AP14819

Maximum rate of take: 4.4ML per day

197 on AP14819

Maximum rate of take: 2.2ML per day

198 on AP14819

Maximum rate of take: 4.4ML per day

199 on AP14819

Maximum rate of take: 4ML per day

200 on AP14819

Maximum rate of take: 4ML per day

201 on AP14819

Maximum rate of take: 4.4ML per day

202 on AP14819

Maximum rate of take: 0.7ML per day

203 on AP14819

Maximum rate of take: 4.4ML per day

204 on AP14819

Maximum rate of take: 4.4ML per day

205 on AP14819

Maximum rate of take: 4ML per day

206 on AP14819

Maximum rate of take: 4ML per day

207 on AP14819

Maximum rate of take: 4ML per day

208 on AP14819

Maximum rate of take: 4.4ML per day

209 on AP14819

Maximum rate of take: 4.4ML per day

210 on AP14819

Maximum rate of take: 4.4ML per day

211 on AP14819

Maximum rate of take: 4.4ML per day

212 on AP14819

Maximum rate of take: 7.4ML per day

213 on AP14819

Maximum rate of take: 4ML per day

214 on AP14819

Maximum rate of take: 2.2ML per day

215 on AP14819

Maximum rate of take: 4.4ML per day

216 on AP14819

Maximum rate of take: 4.4ML per day

217 on AP14819

Maximum rate of take: 2.2ML per day

218 on AP14819

Maximum rate of take: 4.4ML per day

219 on AP14819

Maximum rate of take: 4.4ML per day

220 on AP14819

Maximum rate of take: 2.2ML per day

221 on AP14819

Maximum rate of take: 1.2ML per day

222 on AP14819

Maximum rate of take: 4ML per day

224 on AP14819

Maximum rate of take: 7.4ML per day

225 on AP14819

Maximum rate of take: 13ML per day

226 on AP14819

Maximum rate of take: 4.4ML per day

227 on AP14819

Maximum rate of take: 4.2ML per day

228 on AP14819

Maximum rate of take: 4.4ML per day

229 on AP14819

Maximum rate of take: 4.4ML per day

230 on AP14819

Maximum rate of take: 7.4ML per day

231 on AP14819

Maximum rate of take: 4.4ML per day

232 on AP14819

Maximum rate of take: 4ML per day

233 on AP14819

Maximum rate of take: 2.2ML per day

234 on AP14819

Maximum rate of take: 4.4ML per day

235 on AP14819

Maximum rate of take: 4.4ML per day

236 on AP14819

Maximum rate of take: 4.4ML per day

238 on AP14819

Maximum rate of take: 4.4ML per day

239 on AP14819

Maximum rate of take: 2.2ML per day

240 on AP14819

Maximum rate of take: 4.4ML per day

241 on AP14819

Maximum rate of take: 4.4ML per day

242 on AP14819

Maximum rate of take: 4ML per day

243 on AP14819

Maximum rate of take: 4.4ML per day

244 on AP14819

Maximum rate of take: 4.4ML per day

245 on AP14819

Maximum rate of take: 7.4ML per day

246 on AP14819

Maximum rate of take: 7.4ML per day

247 on AP14819

Maximum rate of take: 4.4ML per day

248 on AP14819

Maximum rate of take: 4.4ML per day

249 on AP14819

Maximum rate of take: 2.2ML per day

250 on AP14819

Maximum rate of take: 4.4ML per day

251 on AP14819

Maximum rate of take: 8.7ML per day

252 on AP14819

Maximum rate of take: 13ML per day

253 on AP14819

Maximum rate of take: 4.4ML per day

254 on AP14819

Maximum rate of take: 4ML per day

255 on AP14819

Maximum rate of take: 2.2ML per day

256 on AP14819

Maximum rate of take: 4.4ML per day

257 on AP14819

Maximum rate of take: 19.1ML per day

258 on AP14819

Maximum rate of take: 4.4ML per day

259 on AP14819

Maximum rate of take: 2.2ML per day

260 on AP14819

Maximum rate of take: 0.7ML per day

262 on AP14819

Maximum rate of take: 2.2ML per day

263 on AP14819

Maximum rate of take: 1.8ML per day

264 on AP14819

Maximum rate of take: 8.3ML per day

265 on AP14819

Maximum rate of take: 4ML per day

266 on AP14819

Maximum rate of take: 1.2ML per day

267 on AP14819

Maximum rate of take: 2.2ML per day

268 on AP14819

Maximum rate of take: 6.5ML per day

271 on AP14819

Maximum rate of take: 1.2ML per day

272 on AP14819

Maximum rate of take: 2.2ML per day

273 on AP14819

Maximum rate of take: 4ML per day

274 on AP14819

Maximum rate of take: 1.2ML per day

275 on AP14819

Maximum rate of take: 2.2ML per day

276 on AP14819

Maximum rate of take: 2ML per day

277 on AP14819

Maximum rate of take: 2ML per day

278 on AP14819

Maximum rate of take: 6.5ML per day

280 on AP14819

Maximum rate of take: 2.2ML per day

282 on AP14819

Maximum rate of take: 2.2ML per day

283 on AP14819

Maximum rate of take: 4ML per day

284 on AP14819

Maximum rate of take: 1.2ML per day

285 on AP14819

Maximum rate of take: 4ML per day

286 on AP14819

Maximum rate of take: 2.2ML per day

287 on AP14819

Maximum rate of take: 4ML per day

288 on AP14819

Maximum rate of take: 4.4ML per day

289 on AP14819

Maximum rate of take: 4.4ML per day

290 on AP14819

Maximum rate of take: 4.4ML per day

291 on AP14819

Maximum rate of take: 4.4ML per day

292 on AP14819

Maximum rate of take: 2.2ML per day

293 on AP14819

Maximum rate of take: 4.4ML per day

294 on AP14819

Maximum rate of take: 2ML per day

296 on AP14819

Maximum rate of take: 4ML per day

298 on AP14819

Maximum rate of take: 1.3ML per day

299 on AP14819

Maximum rate of take: 4ML per day

300 on AP14819

Maximum rate of take: 4.4ML per day

301 on AP14819

Maximum rate of take: 4ML per day

302 on AP14819

Maximum rate of take: 2.2ML per day

304 on AP14819

Maximum rate of take: 2.2ML per day

305 on AP14819

Maximum rate of take: 4ML per day

306 on AP14819

Maximum rate of take: 4.4ML per day

307 on AP14819

Maximum rate of take: 1.2ML per day

308 on AP14819

Maximum rate of take: 1.2ML per day

309 on AP14819

Maximum rate of take: 0.7ML per day

310 on AP14819

Maximum rate of take: 2.2ML per day

311 on AP14819

Maximum rate of take: 4ML per day

312 on AP14819

Maximum rate of take: 1.3ML per day

313 on AP14819

Maximum rate of take: 1.2ML per day

314 on AP14819

Maximum rate of take: 2.2ML per day

315 on AP14819

Maximum rate of take: 0.7ML per day

316 on AP14819

Maximum rate of take: 1.2ML per day

317 on AP14819

Maximum rate of take: 2.2ML per day

318 on AP14819

Maximum rate of take: 4.4ML per day

319 on AP14819

Maximum rate of take: 4ML per day

320 on AP14819

Maximum rate of take: 1.2ML per day

321 on AP14819

Maximum rate of take: 2.2ML per day

322 on AP14819

Maximum rate of take: 2.2ML per day

323 on AP14819

Maximum rate of take: 4ML per day

324 on AP14819

Maximum rate of take: 2.2ML per day

325 on AP14819

Maximum rate of take: 2.2ML per day

327 on AP14819

Maximum rate of take: 2.2ML per day

328 on AP14819

Maximum rate of take: 4ML per day

330 on AP14819

Maximum rate of take: 2.2ML per day

331 on AP14819

Maximum rate of take: 3.5ML per day

332 on AP14819

Maximum rate of take: 4ML per day

333 on AP14819

Maximum rate of take: 2.2ML per day

334 on AP14819

Maximum rate of take: 4.4ML per day

335 on AP14819

Maximum rate of take: 0.2ML per day

336 on AP14819

Maximum rate of take: 6.2ML per day

337 on AP14819

Maximum rate of take: 4.4ML per day

338 on AP14819

Maximum rate of take: 4ML per day

339 on AP14819

Maximum rate of take: 4.4ML per day

340 on AP14819

Maximum rate of take: 4ML per day

341 on AP14819

Maximum rate of take: 4ML per day

342 on AP14819

Maximum rate of take: 2.2ML per day

343 on AP14819

Maximum rate of take: 4ML per day

344 on AP14819

Maximum rate of take: 4.4ML per day

345 on AP14819

Maximum rate of take: 4.4ML per day

346 on AP14819

Maximum rate of take: 4.4ML per day

347 on AP14819

Maximum rate of take: 2.2ML per day

348 on AP14819

Maximum rate of take: 4ML per day

349 on AP14819

Maximum rate of take: 4ML per day

350 on AP14819

Maximum rate of take: 4ML per day

351 on AP14819

Maximum rate of take: 4.4ML per day

352 on AP14819

Maximum rate of take: 1.2ML per day

353 on AP14819

Maximum rate of take: 2.2ML per day

354 on AP14819

Maximum rate of take: 2.2ML per day

355 on AP14819

Maximum rate of take: 4.4ML per day

356 on AP14819

Maximum rate of take: 4.4ML per day

357 on AP14819

Maximum rate of take: 1.5ML per day

359 on AP14819

Maximum rate of take: 2.2ML per day

360 on AP14819

Maximum rate of take: 4ML per day

362 on AP14819

Maximum rate of take: 4.4ML per day

363 on AP14819

Maximum rate of take: 4.4ML per day

364 on AP14819

Maximum rate of take: 6.5ML per day

365 on AP14819

Maximum rate of take: 4.4ML per day

366 on AP14819

Maximum rate of take: 6.5ML per day

Water allocation group: class 5B

367 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 5B

368 on AP14819

Maximum rate of take: 2ML per day

Water allocation group: class 5B

369 on AP14819

Maximum rate of take: 6.5ML per day

Water allocation group: class 5B

370 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 5B

371 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 5B

372 on AP14819

Maximum rate of take: 4.4ML per day

Water allocation group: class 5B

373 on AP14819

Maximum rate of take: 2ML per day

Water allocation group: class 5B

375 on AP14819

Maximum rate of take: 1.3ML per day

Water allocation group: class 6B

376 on AP14819

Maximum rate of take: 4.4ML per day

Water allocation group: class 6B

377 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 6B

378 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 6B

379 on AP14819

Maximum rate of take: 1.2ML per day

Water allocation group: class 6B

380 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 6B

383 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 6B

384 on AP14819

Maximum rate of take: 6.2ML per day

Water allocation group: class 6B

385 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 6B

386 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 6B

387 on AP14819

Maximum rate of take: 4.4ML per day

Water allocation group: class 6B

388 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 6B

389 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 6B

391 on AP14819

Maximum rate of take: 1.2ML per day

Water allocation group: class 6B

392 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 6B

393 on AP14819

Maximum rate of take: 2ML per day

394 on AP14819

Maximum rate of take: 4.4ML per day

395 on AP14819

Maximum rate of take: 4.4ML per day

397 on AP14819

Maximum rate of take: 2.2ML per day

Water allocation group: class 6B

398 on AP14819

Maximum rate of take: 2.2ML per day

399 on AP14819

Maximum rate of take: 4ML per day

400 on AP14819

Maximum rate of take: 1.2ML per day

401 on AP14819

Maximum rate of take: 4ML per day

Water allocation group: class 5B

402 on AP14819

Maximum rate of take: 4.4ML per day

403 on AP14819

Maximum rate of take: 4.4ML per day

404 on AP14819

Maximum rate of take: 4.4ML per day

405 on AP14819

Maximum rate of take: 2.2ML per day

406 on AP14819

Maximum rate of take: 1.1ML per day

407 on AP14819

Maximum rate of take: 0.9ML per day

5025 on AP14819

Maximum rate of take: 3.5ML per day

5026 on AP14819

Maximum rate of take: 0.9ML per day

5030 on AP14819

Maximum rate of take: 17ML per day

5068 on AP14819

Maximum rate of take: 2.2ML per day

5069 on AP14819

Maximum rate of take: 2.2ML per day

Schedule 8 Dictionary

section 3

authorisation means—
(a)a water allocation, water licence, water permit, seasonal water assignment notice or other authority to take water under the Act or the repealed Act, other than a water permit for stock purposes or domestic purposes; or
(b)a water licence or resource operations licence to interfere with water under the Act or the repealed Act.
dam wall, in relation to a dam, means works that include a barrier, whether permanent or temporary, that does, could or would impound water.
decision, for part 6, see section 24.
eWater Source computer program means the eWater Source computer program used by the department to simulate daily stream flows, flow management, storages, releases, in-stream infrastructure, water diversions, water demands and other hydrological events in the plan area.
model computer program means—
(a)the eWater Source computer program; or
(b)a successor of the eWater Source computer program, by whatever name called; or
(c)the statistical analysis and reporting programs associated with a computer program mentioned in paragraph (a) or (b).
node see section 13(1).
nominal entitlement, for a water licence, see the Water Regulation 2016, section 28(1).
plan area see section 6.
simulation period means the period from 1 January 1890 to 30 June 2017.
storage area, in relation to a dam, means the storage area created by the dam wall of the dam.
subcatchments see section 7(1).
supplemented water see the Water Regulation 2016, schedule 19.
surface water see section 4.
Traditional Owners, of an area, means the Aboriginal peoples and Torres Strait Islander peoples who have, under Aboriginal tradition or Island custom, a connection with land and waters in the area.
underground water management area see section 11.
unsupplemented water means water that is not supplemented water.
water supply scheme zone see section 8(3).